Project: CRIME PREVENTION PROJECT

REPORT BY: Charlie Hartnett

HBW SILO

loader-image
Lidl Luton
2:17 pm, May 2, 2025
temperature icon 24°C
few clouds
Humidity 51 %
Wind Gust: 5 mph

click here to watch

DAY: 4

REPORT DATE: March 31, 2023

TIME SCHEDULE

Installation Progress On Time

STORED MATERIAL

Completeness
Intactness
Cleanliness
Appropriate Storage

INSTALLED MATERIAL

Intactness
Cleanliness

TESTINGS

Anchor Testing
Bolt Fixation Testing
Damages
Month
Near Miss
Incidents
Accidents
Daily Project Status
Total Percentage
100
Actual Percentage
25
Target Percentage
0%
Actual Percentage
0%

IMAGES

DAILY LOG BOOK LIDL LUTON

Men on Site
4
UNITS INSTALLED
7%

Quality Issues
(If yes, comments below)

On arrival the materials were no loaded in the aisles. Our operatives loaded the material to keep progress on site. Operators were obstructed by netting so set up the lines where possible. This meant when the netting was removed we had to re set up tension lines in these areas. Chargeable Time lost= 4 hours

progress chart

Climbing Works
- Aisles

A SIDE CONNECTIONS

B SIDE CONNECTIONS

A ZONES

Rope Access Works -
Above Mezzanine

Climbing Works - Aisles

B ZONES

Rope Access Works -
Above Mezzanine

Climbing Works - Aisles

Rope Access Works -
Above Mezzanine

Project Manager's Comments

[wpse_comments_template]
For mobile viewing, rotate your phone to landscape
0
Would love your thoughts, please comment.x
()
x

DUPLICATE REPORT

No Data For This Week

scaling solutions logo
Comments/Notes
Subscribe
Notify of