Project: CRIME PREVENTION PROJECT

REPORT BY: Charlie Hartnett

HBW SILO

loader-image
Lidl Luton
12:34 pm, May 2, 2025
temperature icon 23°C
clear sky
Humidity 62 %
Wind Gust: 0 mph

click here to watch

DAY: 39

REPORT DATE: June 1, 2023

TIME SCHEDULE

Installation Progress On Time

STORED MATERIAL

Completeness
Intactness
Cleanliness
Appropriate Storage

INSTALLED MATERIAL

Intactness
Cleanliness

TESTINGS

Anchor Testing
Bolt Fixation Testing
Damages
Month
Near Miss
Incidents
Accidents
Daily Project Status
Total Percentage
100
Actual Percentage
50
Target Percentage
0%
Actual Percentage
0%

IMAGES

DAILY LOG BOOK LIDL LUTON

Men on Site
4
UNITS INSTALLED
22%

Quality Issues
(If yes, comments below)

Only can access aisles 7&8 asides and work completed by 12. JH wont allow any other access.. Cannot set up Bsides as all of our lines are set up ready in the Aside. lus Time Lost 5 hours

progress chart

Climbing Works
- Aisles

A SIDE CONNECTIONS

B SIDE CONNECTIONS

A ZONES

Rope Access Works -
Above Mezzanine

Climbing Works - Aisles

B ZONES

Rope Access Works -
Above Mezzanine

Climbing Works - Aisles

Rope Access Works -
Above Mezzanine

Project Manager's Comments

[wpse_comments_template]
For mobile viewing, rotate your phone to landscape
1
0
Would love your thoughts, please comment.x
()
x

DUPLICATE REPORT

No Data For This Week

scaling solutions logo
Comments/Notes
Subscribe
Notify of